In short
Councils have 13 weeks to decide major applications and 8 weeks for most others, but those periods are often extended by agreement and they only start once a complete application is submitted. For a landowner, the more useful figure is the time from starting work on the site to planning permission. On a site that can go straight to an application, that is often two to three years. Where land has to be allocated in a local plan first, five to eight years is common. Surveys, Section 106 agreements, appeals and the six-week challenge period all add time, and option agreements are written to allow for them.
Ask AI to summariseChatGPTClaudePerplexityGoogle AI
The Short Answer: Typical Timescales by Route
Most landowners are surprised by how long planning takes. The decision itself is only one stage. Before it come surveys, design and pre-application talks. After it come legal agreements, a challenge period and the sale. The route your land takes matters more than anything else.
| Route | Typical time to planning permission | Best suited to |
|---|---|---|
| Application where the council is short of homes | 18 months to 3 years | Land well related to a settlement in a district with unmet housing need |
| Grey belt or previously developed land | 2 to 4 years | Green Belt land that does not strongly serve Green Belt purposes, or old yards |
| Allocation through a local plan, then an application | 5 to 8 years, sometimes longer | Larger sites, and land in districts meeting their housing numbers |
| Any of the above with an appeal | Add 6 to 12 months | Sites refused by the council, or not decided in time |
Statutory Decision Periods
Once a valid application is submitted, the law sets a period for the council to make a decision. As they stood when we checked in September 2026, these are:
| Type of application | Statutory period |
|---|---|
| Major development (10 or more homes, or a site of 0.5 hectares or more) | 13 weeks |
| Development needing an Environmental Impact Assessment | 16 weeks |
| Most other applications, including smaller housing schemes | 8 weeks |
| Approval of details reserved by condition | 8 weeks |
In practice, many major applications take longer. The council and the applicant can agree in writing to extend the period, known as an extension of time, and this is very common while issues are worked through or a Section 106 agreement is drafted. For larger schemes, a planning performance agreement sets out an agreed timetable, and government guidance encourages one to be agreed before submission.
There is also a backstop, called the planning guarantee. Major applications should be decided within 26 weeks and others within 16 weeks. If they are not, and no longer period has been agreed, the application fee is refunded.
If the council has not decided within the statutory period, or an agreed extension, the applicant can appeal for non-determination. That means the Planning Inspectorate takes over the decision. Once that appeal is lodged the council can no longer decide the application itself, so it is used carefully.
Route One: A Planning Application Straight Away
Where the council is short of homes, or the land falls within a national policy that supports development, an application can be made without waiting for a local plan. A typical sequence:
- Surveys and technical work, 6 to 12 months. Ecology, access, drainage, landscape, heritage, trees, ground conditions and a Biodiversity Net Gain assessment. Some ecology surveys can only be done at certain times of year, which often decides the timetable.
- Pre-application advice, 2 to 4 months. Talking to the council, highway authority and others before submission saves time later.
- Validation, a few days to a few weeks. The council checks the application is complete. Since August 2026, Annex C of the NPPF sets a national list of information, which limits what councils can demand.
- Consultation and assessment. Neighbours and consultees such as the highway authority and the lead local flood authority comment. The public consultation period is normally 21 days, but consultee responses and amended plans often take much longer.
- Committee. Larger or contested schemes go to the planning committee, which usually meets monthly. A resolution to grant is not yet a permission.
- Section 106 agreement. The permission is issued once the legal agreement is signed.
From instruction to issued permission, 18 months to three years is realistic for a well-prepared site. Land that is less straightforward, or in a district with long consultee delays, can take longer. Our guide to the August 2026 NPPF explains when this route is open.
The usual evidence that a council is short of homes is a Housing Delivery Test result below 75% or a supply of housing land under five years. On the latest figures, these councils on our area pages show one or both. That evidence is weighed with everything else about the site, and it does not open this route in the Green Belt.
- Bedforddelivery 94%, supply 3.35 years
- Central Bedfordshiredelivery 105%, supply 3.93 years
- Lutondelivery 54%, supply 4.64 years
- Bracknell Forestdelivery 104%, supply 3.53 years
- Readingdelivery 136%, supply 3.55 years
- Sloughdelivery 54%, supply 2.51 years
- Windsor and Maidenheaddelivery 74%, supply 4.04 years
- Wokinghamdelivery 100%, supply 2.5 years
- Buckinghamshiredelivery 94%, supply 3.73 years
- Cambridgedelivery 82%, supply 2.72 years
- Huntingdonshiredelivery 136%, supply 3.68 years
- Peterboroughdelivery 100%, supply 4.38 years
- Cheshire Eastdelivery 213%, supply 3.3 years
- Cheshire West and Chesterdelivery 244%, supply 1.6 years
- Bolsoverdelivery 205%, supply 4.82 years
- Chesterfielddelivery 168%, supply 3.46 years
- Derbydelivery 71%, supply 2.39 years
- Derbyshire Dalesdelivery 90%, supply 1.36 years
- Erewashdelivery 49%, supply 1.6 years
- High Peakdelivery 121%, supply 2.78 years
- North East Derbyshiredelivery 268%, supply 4.47 years
- Brighton and Hovedelivery 50%, supply 1.5 years
- Eastbournedelivery 23%, supply 1.4 years
- Hastingsdelivery 44%, supply 1.65 years
- Lewesdelivery 60%, supply 2.73 years
- Rotherdelivery 35%, supply 3.04 years
- Wealdendelivery 89%, supply 3.65 years
- Basildondelivery 23%, supply 1.96 years
- Castle Pointdelivery 11%, supply 0.91 years
- Chelmsforddelivery 110%, supply 4.74 years
- Colchesterdelivery 109%, supply 3.37 years
- Epping Forestdelivery 66%, supply 4.22 years
- Harlowdelivery 91%, supply 4.9 years
- Maldondelivery 143%, supply 4.1 years
- Rochforddelivery 111%, supply 1.97 years
- Southend-on-Seadelivery 20%, supply 1.3 years
- Tendringdelivery 152%, supply 3.52 years
- Thurrockdelivery 29%, supply 1.02 years
- Uttlesforddelivery 108%, supply 4.77 years
- Cheltenhamdelivery 56%, supply 2.69 years
- Cotswolddelivery 68%, supply 1.8 years
- Forest of Deandelivery 128%, supply 1.93 years
- Gloucesterdelivery 63%, supply 3.1 years
- South Gloucestershiredelivery 138%, supply 3.93 years
- Strouddelivery 85%, supply 3.24 years
- Tewkesburydelivery 219%, supply 3.65 years
- Basingstoke and Deanedelivery 94%, supply 3.1 years
- East Hampshiredelivery 79%, supply 2.9 years
- Eastleighdelivery 94%, supply 4.2 years
- Farehamdelivery 60%, supply 2.99 years
- Gosportdelivery 25%, supply 1.87 years
- Hartdelivery 137%, supply 2.07 years
- Havantdelivery 80%, supply 1.3 years
- New Forestdelivery 48%, supply 1.53 years
- Portsmouthdelivery 11%, supply 2.4 years
- Rushmoordelivery 176%, supply 4.74 years
- Southamptondelivery 30%, no supply figure
- Test Valleydelivery 64%, supply 2.54 years
- Herefordshiredelivery 96%, supply 2.81 years
- Broxbournedelivery 110%, supply 2.13 years
- Dacorumdelivery 52%, supply 1.2 years
- East Hertfordshiredelivery 102%, supply 2.88 years
- Hertsmeredelivery 26%, supply 0.98 years
- North Hertfordshiredelivery 75%, supply 2.6 years
- St Albansdelivery 46%, supply 1.12 years
- Three Riversdelivery 47%, supply 1.2 years
- Welwyn Hatfielddelivery 46%, supply 1.8 years
- Ashforddelivery 75%, supply 3.16 years
- Canterburydelivery 79%, supply 3.62 years
- Folkestone and Hythedelivery 57%, supply 3.1 years
- Graveshamdelivery 61%, supply 2.53 years
- Maidstonedelivery 93%, supply 4.5 years
- Medwaydelivery 60%, supply 3.1 years
- Sevenoaksdelivery 25%, supply 3.59 years
- Swaledelivery 70%, supply 3.48 years
- Thanetdelivery 70%, supply 3.7 years
- Tonbridge and Mallingdelivery 63%, supply 2.89 years
- Tunbridge Wellsdelivery 93%, supply 4.7 years
- Blabydelivery 86%, supply 2.78 years
- Charnwooddelivery 62%, supply 3.56 years
- Harboroughdelivery 139%, supply 3.1 years
- Hinckley and Bosworthdelivery 134%, supply 4.48 years
- Leicesterdelivery 39%, supply 5.16 years
- Bostondelivery 127%, supply 4.8 years
- East Lindseydelivery 129%, supply 2.33 years
- North East Lincolnshiredelivery 244%, supply 3.6 years
- South Hollanddelivery 161%, supply 4.6 years
- South Kestevendelivery 97%, supply 4.07 years
- Brecklanddelivery 144%, supply 2.82 years
- Broadlanddelivery 111% (joint area), supply 4.85 years
- North Norfolkdelivery 54%, supply 7.3 years
- Norwichdelivery 111% (joint area), supply 4.85 years
- South Norfolkdelivery 111% (joint area), supply 4.85 years
- North Northamptonshiredelivery 108%, supply 4.6 years
- West Northamptonshiredelivery 104%, supply 4.3 years
- Ashfielddelivery 93%, supply 3.66 years
- Broxtowedelivery 109%, supply 4.85 years
- Gedlingdelivery 125%, supply 3.73 years
- Newark and Sherwooddelivery 139%, supply 3.84 years
- Cherwelldelivery 134%, supply 3.1 years
- Oxforddelivery 65%, supply 2.88 years
- South Oxfordshiredelivery 171%, supply 3.98 years
- Rutlanddelivery 89%, supply 4.34 years
- Shropshiredelivery 124%, supply 4.61 years
- Lichfielddelivery 232%, supply 3.5 years
- South Staffordshiredelivery 171%, supply 0.87 years
- Stafforddelivery 149%, supply 1.95 years
- Staffordshire Moorlandsdelivery 160%, supply 2.95 years
- Stoke-on-Trentdelivery 66%, supply 3.73 years
- Tamworthdelivery 220%, supply 1.6 years
- Baberghdelivery 147%, supply 4.68 years
- East Suffolkdelivery 91%, supply 3.07 years
- Ipswichdelivery 63%, supply 3.46 years
- Elmbridgedelivery 59%, supply 1 year
- Epsom and Ewelldelivery 33%, supply 1.49 years
- Guildforddelivery 102%, supply 2.98 years
- Mole Valleydelivery 72%, supply 5.3 years
- Reigate and Bansteaddelivery 102%, supply 4.08 years
- Runnymededelivery 94%, supply 2.89 years
- Spelthornedelivery 33%, supply 5.3 years
- Tandridgedelivery 38%, supply 2.17 years
- Waverleydelivery 117%, supply 1.28 years
- North Warwickshiredelivery 164%, supply 1.5 years
- Rugbydelivery 187%, supply 3.4 years
- Stratford-on-Avondelivery 202%, supply 2.21 years
- Warwickdelivery 128%, supply 1.96 years
- Birminghamdelivery 57%, supply 6.45 years
- Coventrydelivery 47%, supply 5.91 years
- Sandwelldelivery 34%, supply 1.86 years
- Solihulldelivery 53%, supply 2.13 years
- Walsalldelivery 56%, supply 1.97 years
- Wolverhamptondelivery 59%, no supply figure
- Adurdelivery 48%, supply 3.2 years
- Arundelivery 84%, supply 3.41 years
- Chichesterdelivery 124%, supply 4.52 years
- Crawleydelivery 36%, no supply figure
- Horshamdelivery 44%, supply 1.7 years
- Mid Sussexdelivery 104%, supply 3.75 years
- Bromsgrovedelivery 58%, supply 2.24 years
- Redditchdelivery 129%, supply 3.11 years
Councils on our area pages only. Supply is each council's latest published figure, or the latest tested at appeal; Housing Delivery Test 2025 published 17 August 2026.
Route Two: Allocation Through a Local Plan
Under the new plan-making system that began on 25 March 2026, councils are expected to prepare plans within 30 months. That is faster than many plans managed under the old system, but for a landowner it is only part of the story.
If your land is submitted early in the process, the plan might be adopted two and a half years later if the timetable holds. Timetables often slip. After adoption, an application still has to be prepared and decided, which typically adds another 18 months to two years. Five to eight years from first submission to permission is common, and land that just misses one plan may have to wait for the next.
The advantage is certainty of principle. An allocated site that follows the plan's policy has a very good chance of approval. Our guide to call for sites and local plans explains each stage.
In councils that are meeting most of their housing target and can show five years of land, this slower route is usually the surer one. These are the councils on our area pages in that position.
- West Berkshiredelivery 114%, supply 5.7 years
- Milton Keynesdelivery 142%, supply 5.47 years
- East Cambridgeshiredelivery 116%, supply 6.17 years
- Fenlanddelivery 117%, supply 6.6 years
- South Cambridgeshiredelivery 148%, supply 7.83 years
- Warringtondelivery 134%, supply 5.13 years
- Amber Valleydelivery 173%, supply 5.8 years
- South Derbyshiredelivery 195%, supply 5.27 years
- Winchesterdelivery 174%, supply 5.5 years
- Meltondelivery 190%, supply 7.6 years
- North West Leicestershiredelivery 184%, supply 5.1 years
- Oadby and Wigstondelivery 152%, supply 6.68 years
- Lincolndelivery 141% (joint area), supply 7.1 years
- North Kestevendelivery 141% (joint area), supply 7.1 years
- North Lincolnshiredelivery 137%, supply 5.07 years
- West Lindseydelivery 141% (joint area), supply 7.1 years
- Great Yarmouthdelivery 92%, supply 6.06 years
- King's Lynn and West Norfolkdelivery 100%, supply 6.2 years
- Bassetlawdelivery 357%, supply 5.31 years
- Mansfielddelivery 134%, supply 6.59 years
- Nottinghamdelivery 108%, supply 6.57 years
- Rushcliffedelivery 172%, supply 5.1 years
- Vale of White Horsedelivery 192%, supply 5.26 years
- Telford and Wrekindelivery 309%, supply 6.02 years
- Cannock Chasedelivery 115%, supply 5 years
- East Staffordshiredelivery 181%, supply 5.06 years
- Newcastle-under-Lymedelivery 94%, supply 7.57 years
- Mid Suffolkdelivery 227%, supply 6.73 years
- West Suffolkdelivery 89%, supply 6.02 years
- Surrey Heathdelivery 98%, supply 7.17 years
- Wokingdelivery 97%, supply 8.1 years
- Nuneaton and Bedworthdelivery 221%, supply 10.2 years
- Dudleydelivery 92%, supply 5.1 years
- Worthingdelivery 142%, supply 6.9 years
- Malvern Hillsdelivery 101%, supply 5.48 years
- Worcesterdelivery 88%, supply 5.48 years
- Wychavondelivery 103%, supply 5.48 years
- Wyre Forestdelivery 212%, supply 8.8 years
Councils on our area pages only. Supply is each council's latest published figure, or the latest tested at appeal; Housing Delivery Test 2025 published 17 August 2026.
Outline Permission, Then Reserved Matters
Most land is sold with outline planning permission. Outline permission establishes the principle and usually the access and the maximum number of homes. The detail, such as layout, appearance, scale and landscaping, is left as "reserved matters", to be applied for later once the detailed scheme is designed.
Under the standard time limits, an application for approval of reserved matters must be made within three years of the outline permission, and development must begin within two years of the final approval of reserved matters. A full permission must usually be started within three years. Councils can set different periods.
This matters to you because a sale under an option usually completes on the strength of outline permission. The reserved matters are dealt with afterwards, so the detailed design of the houses is not something you have to wait for.
If you are keeping land next to the site, look at the parameter plans submitted with the outline application. They show where the access, the built area and the open space are expected to go, and the later reserved matters normally have to stay within them. That tells you early how the new homes will sit against the fields or garden you keep.
Appeals
If the council refuses permission, the applicant can appeal to the Planning Inspectorate. Most planning appeals must be made within six months of the decision notice. Householder and minor commercial appeals have only 12 weeks.
Appeals are decided by written representations, a hearing or a public inquiry. Official statistics for April 2025 to March 2026 give these median times to decide:
| Procedure | Median time | Mean time |
|---|---|---|
| Written representations | 20 weeks | 28.8 weeks |
| Hearings | 24 weeks | 32.3 weeks |
| Inquiries | 28 weeks | 40.1 weeks |
| All appeals | 21 weeks | 30.1 weeks |
The mean is well above the median, which tells you some appeals take much longer. Preparing an appeal also takes time before it is lodged. Allowing six to twelve months for an appeal, from refusal to decision, is prudent.
After a decision, whether by the council or an inspector, there is a six-week window in which a third party can bring a legal challenge in the High Court. Buyers normally wait for that period to pass before completing.
Section 106 Agreements
A Section 106 agreement is a legal agreement that secures affordable housing, contributions to schools and roads, open space and other obligations. There is no statutory deadline for agreeing one. It can take anything from a few weeks to many months, depending on the number of parties, the council's legal team, and whether the county council is involved. Some councils set a deadline in the committee resolution, after which the application can be refused if the agreement has not been signed, so it pays to have title documents and plans ready early.
As the landowner, you will usually need to sign it, because the obligations bind the land. We run the Section 106 negotiations as part of the planning work, and we contribute to your own solicitor's fees, so the cost of doing it properly is shared with us. Our guide to Section 106 and CIL explains what these agreements contain.
Discharge of Conditions
Planning permissions come with conditions, and many must be dealt with before work starts, for example approving a construction management plan or drainage details. The council has 8 weeks to decide an application to discharge conditions, or longer if agreed in writing. If no decision is made within 12 weeks, the fee must be refunded, and for many conditions there is a deemed discharge procedure the applicant can use.
Conditions are usually the buyer's concern after completion, not yours. They matter to you only where the sale is conditional on them, which is uncommon for outline land deals.
What Causes Delay
- Survey seasons. Missing the window for a protected species survey can add most of a year.
- Highway and drainage objections. Access and surface water are the most common technical reasons for delay.
- Consultee backlogs. Some bodies take weeks or months to respond, and amended plans restart parts of the process.
- Environmental issues specific to the area. Nutrient neutrality, water supply or protected habitats can hold up whole districts.
- Committee cycles. Missing one monthly committee usually means waiting for the next.
- Section 106 negotiations. Especially where several councils or landowners must sign.
- Changes in policy or housing numbers. A council's supply position can change during an application.
- Title problems. Unregistered land, missing access rights or disputes between co-owners. See our guide to access and ransom strips.
From First Call to Completion: An Example
| Stage | Typical duration | Running total (illustrative) |
|---|---|---|
| First call and free desktop review | 2 to 4 weeks | Month 1 |
| Heads of terms agreed | 1 to 2 months | Month 3 |
| Option agreement signed, after your solicitor has reviewed it | 2 to 4 months | Month 6 |
| Surveys, design and pre-application advice | 6 to 12 months | Month 15 |
| Application submitted, to resolution to grant | 4 to 9 months | Month 22 |
| Section 106 signed and permission issued | 1 to 4 months | Month 25 |
| Six-week challenge period passes | 6 weeks | Month 27 |
| Option exercised and purchase completes | Set out in your agreement | Once permission is secured |
In this example planning permission is secured a little over two years after the first phone call. Some sites are quicker and many are slower, and nobody can promise the date of a council decision.
The work does not run at an even pace, and it helps to know that in advance. There are short, busy spells when surveyors are on the land or the application is submitted, followed by long quiet months while reports are written, consultees respond and the committee date is set. A quiet month usually means the application is waiting its turn, not that it has stalled.
How Our Agreements Allow for These Timescales
Because nobody can fix the date of a planning decision, our agreements are written around the planning process rather than around a date on the calendar.
- Planned for the route your land needs. A site that can go straight to an application and a site that needs the local plan first are planned differently from the start, and we explain which route we expect to take before anything is signed.
- It continues while decisions are made. If a planning application or appeal is being decided, the agreement continues until it is. Years of work are never lost a week before a decision.
- Satisfactory permission. This usually requires the six-week challenge period to have passed without a challenge, which is why completion follows some weeks after the decision.
Our guide to option agreements explains how they work in more detail.
How We Handle This
Before we agree terms, our planners look at which route suits your land and give you an honest view of the likely timescale to planning permission. We then pay for and run all the planning work, at our own cost and risk, and we report progress to you in writing at each stage.
While the work runs, we deal with the council, the consultants, the highway authority and the consultations. You do not need to attend meetings or read technical reports, although you are always welcome to, and we tell you before anything about your land becomes public.
Families often ask what happens if the land passes on while planning is under way. The agreement binds your estate, so your executors step into your position and the agreed price is paid to your estate on completion. See our page on inherited land.
Common Questions
How long does it take to get planning permission for houses?
The council has 8 weeks to decide most smaller applications and 13 weeks for major ones of 10 or more homes, but that clock only starts once a valid application is in, and extensions are common. For development land, allow roughly 18 months to 3 years from starting work where the council is short of homes, and 5 to 8 years where the land has to go through a local plan first.
Is the 13-week deadline a guarantee?
No. It is the statutory period, but it is often extended by agreement. The planning guarantee means the fee is refunded if a major application is not decided within 26 weeks without an agreed extension.
Can I carry on farming while planning is pursued?
Usually, yes. Under an option you keep using the land until completion, although surveyors will need access.
Does an appeal always add a year?
Not always. In the year to March 2026, the median appeal by written representations took 20 weeks to decide. Inquiries take longer, and preparation time comes first.
When do I get paid?
On completion, once planning permission has been secured and the option is exercised. The payment milestones are set out in the agreement, and if permission is not achieved you keep your land and owe nothing.
Can the process be speeded up?
Good preparation helps most: surveys done in season, early talks with the council and highway authority, and a clean title. Nobody can control committee dates or appeal queues.
If you would like an honest view of how long your land might take, ask for a free review.
How This Works in Your Area
The rules are national, but each council's housing numbers and local plan decide how strong the case for a site is. Choose your county to see where each of its councils stands.
- Oxfordshire
- Buckinghamshire
- Hampshire
- Surrey
- Kent
- Cambridgeshire
- Bedfordshire
- Hertfordshire
- Essex
- Warwickshire
- Worcestershire
- Northamptonshire
- Leicestershire
- Nottinghamshire
- Derbyshire
- Gloucestershire
- Wiltshire
- Cheshire
- West Sussex
- Berkshire
- Suffolk
- Norfolk
- East Sussex
- Staffordshire
- Rutland
- Herefordshire
- Shropshire
- West Midlands
- Lincolnshire
This guide is general information about planning policy in England, not advice on a particular site. Policy changes, so check the current position.